Alphanumeric Naming Convention (also Schedule File Name Convention)

by Don Jabinal | Innovation | 2023-05-01

Alphanumeric Naming Convention (also Schedule File Name Convention)

Illustration 3.2 Schedule file name convention for identification of schedule versions

Alphanumeric Naming Convention is a convenient format to monitor the number of schedule submissions, schedule version history, and version control - as well as, to obtain a snapshot of the project's performance for every schedule submission. As part of the schedule version history, the source of schedule submissions is also tracked.

Every schedule submission (schedule version) is assigned a combination of a unique number (Month Identifier), and an alphabet (Baseline Series Identifier).

The number in the schedule version refers to the progress as of the number of months from the project start. The number for the month is derived from the data date.

The alphabet in the schedule version such as A, B, or J helps to differentiate schedule submissions.

  • Major developments in the schedule version history, major schedule logic changes, and proposed baselines/ accepted baselines are identified with a unique alphabet which is called a baseline series identifier
  • The alphabet is used to recognize the source of the schedule versions.
  • The alphabet is also used to track schedule versions where major changes in logic, duration, or forecast dates might have happened.
  • With the help of the alphabet identifier, schedule versions with similar attributes, functionality, logic, etc. (part of the same baseline) can be easily marked, and grouped, if needed.

It is a best practice that also helps avoid confusion - a comparative analysis of a project's schedule data may involve source data by the contractor, data from other sources in the project, and secondary data generated by third parties.

Month Month & Year Schedule Version Data Date Print Date Substantial Completion (MS85) Slippage Note
0Aug 20210-A Contractor's Draft Schedule2021-09-13 (assumed)2021-09-072023-12-29Contractor's Draft Schedule. Submitted by Percon on 2021-09-07.
0Aug 20210-B Contractor's Draft Schedule2021-10-04 (assumed)2021-10-052023-12-29Contractor's Baseline Schedule. Submitted by Percon on 2021-10-05.
1Sep 2021
2Oct 2021
3Nov 20213-C Schedule Update2021-11-12 (assumed)2021-11-122024-02-14-48 cd / -33 wdFirst schedule submission for Nov 2021. Showed delay due to contaminated fill.
3Nov 20213-D Schedule Update2021-11-26 (assumed)2021-11-262024-02-23-57 cd / -393 wdSecond schedule submission for Nov 2021. Showed delay due to contaminated fill.
4Dec 2021
5Jan 2022
6Feb 20226-D Schedule Update2022-02-10 (assumed)2022-02-102024-04-08-102 cd / -69 wdShowed delay due to contaminated fill.
7March 2022
8April 20228-D Schedule Update2022-04-11 (assumed)2022-04-212024-05-03-127 cd / -88 wdShowed delay in parking garage forming due to strike of truckers/haulers.
9May 2022
10June 202210-D Schedule Update2022-06-24 (assumed)2022-06-302024-07-04-189 cd / -130 wdTotal actual schedule progress was 50% lower than planned.
11-14Jul-Oct 2022
15Nov 202215-D Schedule Update2022-11-08 (assumed)2022-11-172024-08-27-243 cd / -168 wdAdditional delay of 54 cd to Substantial Completion.
16Dec 2022
17Jan 202317-D Schedule Update2023-01-30 (assumed)2023-02-092024-07-24-209 cd / -144 wd34 cd of schedule gain (delay mitigation) reported.