Illustration 3.2 Schedule file name convention for identification of schedule versions
Alphanumeric Naming Convention is a convenient format to monitor the number of schedule submissions, schedule version history, and version control - as well as, to obtain a snapshot of the project's performance for every schedule submission. As part of the schedule version history, the source of schedule submissions is also tracked.
Every schedule submission (schedule version) is assigned a combination of a unique number (Month Identifier), and an alphabet (Baseline Series Identifier).
The number in the schedule version refers to the progress as of the number of months from the project start. The number for the month is derived from the data date.
The alphabet in the schedule version such as A, B, or J helps to differentiate schedule submissions.
- Major developments in the schedule version history, major schedule logic changes, and proposed baselines/ accepted baselines are identified with a unique alphabet which is called a baseline series identifier
- The alphabet is used to recognize the source of the schedule versions.
- The alphabet is also used to track schedule versions where major changes in logic, duration, or forecast dates might have happened.
- With the help of the alphabet identifier, schedule versions with similar attributes, functionality, logic, etc. (part of the same baseline) can be easily marked, and grouped, if needed.
It is a best practice that also helps avoid confusion - a comparative analysis of a project's schedule data may involve source data by the contractor, data from other sources in the project, and secondary data generated by third parties.
| Month | Month & Year | Schedule Version | Data Date | Print Date | Substantial Completion (MS85) | Slippage | Note |
|---|---|---|---|---|---|---|---|
| 0 | Aug 2021 | 0-A Contractor's Draft Schedule | 2021-09-13 (assumed) | 2021-09-07 | 2023-12-29 | Contractor's Draft Schedule. Submitted by Percon on 2021-09-07. | |
| 0 | Aug 2021 | 0-B Contractor's Draft Schedule | 2021-10-04 (assumed) | 2021-10-05 | 2023-12-29 | Contractor's Baseline Schedule. Submitted by Percon on 2021-10-05. | |
| 1 | Sep 2021 | ||||||
| 2 | Oct 2021 | ||||||
| 3 | Nov 2021 | 3-C Schedule Update | 2021-11-12 (assumed) | 2021-11-12 | 2024-02-14 | -48 cd / -33 wd | First schedule submission for Nov 2021. Showed delay due to contaminated fill. |
| 3 | Nov 2021 | 3-D Schedule Update | 2021-11-26 (assumed) | 2021-11-26 | 2024-02-23 | -57 cd / -393 wd | Second schedule submission for Nov 2021. Showed delay due to contaminated fill. |
| 4 | Dec 2021 | ||||||
| 5 | Jan 2022 | ||||||
| 6 | Feb 2022 | 6-D Schedule Update | 2022-02-10 (assumed) | 2022-02-10 | 2024-04-08 | -102 cd / -69 wd | Showed delay due to contaminated fill. |
| 7 | March 2022 | ||||||
| 8 | April 2022 | 8-D Schedule Update | 2022-04-11 (assumed) | 2022-04-21 | 2024-05-03 | -127 cd / -88 wd | Showed delay in parking garage forming due to strike of truckers/haulers. |
| 9 | May 2022 | ||||||
| 10 | June 2022 | 10-D Schedule Update | 2022-06-24 (assumed) | 2022-06-30 | 2024-07-04 | -189 cd / -130 wd | Total actual schedule progress was 50% lower than planned. |
| 11-14 | Jul-Oct 2022 | ||||||
| 15 | Nov 2022 | 15-D Schedule Update | 2022-11-08 (assumed) | 2022-11-17 | 2024-08-27 | -243 cd / -168 wd | Additional delay of 54 cd to Substantial Completion. |
| 16 | Dec 2022 | ||||||
| 17 | Jan 2023 | 17-D Schedule Update | 2023-01-30 (assumed) | 2023-02-09 | 2024-07-24 | -209 cd / -144 wd | 34 cd of schedule gain (delay mitigation) reported. |